Settlements Paradigm
Vertically Integrated Utility (in Market)
Generation
103 MWH
Load
100 MWH
Cost of Generation@
$ 25/MWH
$2575
Cost of Transmission@
$ 2/MWH
$206
Revenue from Load@
$ 30/MWH
$3000
LMP
Payment @
$120/MWH
$12360
FTR
Payment @
$2/MWH
$206
Loss
Refund @
$3.6/MWH
$360
LMP
Charge @
$129.26/MWH
$12926